Basement: Difference between revisions

From Adam Colton
Jump to navigation Jump to search
 
(38 intermediate revisions by the same user not shown)
Line 1: Line 1:
Project plan for the basement
Project plan for the basement


# Clean basement out
# Glue up insulation
# Tear everything out
# Install furring
# Schedule mold removal & electrical
# Rewire lighting
# Hang drywall
# Install floors
# Tape drywall
# install gantry base
# paint drywall
# install ceiling
# Build bar and cabinets
# Install hardboard
# install floors
# Install MDF battens
# install baseboard and molding
# Install bead work
# Caulk / fill
# Prime
# Paint
 
I also think I want to put in the floor before the drywall so it can go under it a little. But I should put in and seal the bottom piece first.
 
== Build ==
Can Do
* Finish horizontal furrings
* Vertical furrings
* Wire lights
* Ceiling
 
Subfloor prep
* Clear garage
* Clear basement
* Test finish
 
4/4/20 Subfloor
* Buy materials
* return truck
* Cut support strips to width
* Cut strips to length
* Install
 
4/4/20 Shopping
* brad nailer
* brads
* 10 sheets 1" insulation
* 10 sheets 1/2" OSB
* 10 sheets 1/8" plywood veneer
* 2 sheets 3/4" plywood
* moisture barrier & tape (322 sqft)
 
Reference
* [https://www.youtube.com/watch?v=i48Tdi4H1TY Furring Strips]
* [https://www.youtube.com/watch?v=7nBkV4ecWos Floor Insulation]
 
== Lights ==
I want to move the lights from the ceiling to wall sconces. To run this behind the furring requires that I use mc cabling.


== Bar/Cabinets ==
== Bar/Cabinets ==
I'll need to get exact measurements, but I want two taller cabinets at each end, a working space in the middle with shallow shelves. An open space underneath for a mini-fridge. The left-hand cabinet will hide the ugly pipe (but leave it accessible) and the right hand cabinet will hold the electronics as well as having a space for a laundry basket under the chute.
The entire space will be storage. One tall cabinet, a wine cabinet, fold down bar and a tall cabinet.


I'm just going to buy cabinetry from HD.
The cabinets should be fairly straight forward, though I'm a bit nervous about the hinges.


[http://www.wilcoxdyerelectric.com/contact.php Electrical] Need to get another circuit down there.
The wine cabinet will have glass and lighting, possibly temperature control.
 
The bar will be the complicated part. The bottom will just be a cabinet with a fridge. The top will be a fold down bar. I'd really like a parallel mechanism for the legs, but I'm not sure that's possible.
 
I also need a lock for the wine cabinet and the bar. I think I could do this with servos.


== TV ==
== TV ==
Line 24: Line 68:


== Floor ==
== Floor ==
There was a lot of moisture under the floor. I really need to get the gutter situation fixed.
First, put down a moisture barrier. Leave a bit around the edges.


I could put in a dimpled subfloor like [http://www.homedepot.com/p/DMX-1-STEP-100-sq-ft-44-in-x-27-ft-6-in-Unique-Air-Gap-Underlayment-Prevents-Mold-and-Mildew-DMX-1-Step/204494289 this]. I'll need 4 rolls.
The subfloor will contain the insulation. I think this will be easiest to build in the garage then assemble in the basement. Each section is the size of a sheet of OSB, except for the area around the edges. Each section has a frame running around the edges and two down the center for support. Alex is coming up on 4/4/20 to help with this.


=== Update ===
The surface will be thin plywood cut in 6" strips. After cutting, I'll go back over the board and cut a slight chamfer to create a small gap between the boards. The strips can be sanded in the garage. I'll stain and seal them in the basement. I'll need to do a few tests. My plan is a darker stain and oil base poly seal. My plan is to just glue the floor down.
We painted the floor with an epoxy paint, but it's not very durable. I think I'll finish the rest of the basement as is, but when it's done, I'll go back and put in a linoleum floor. Even if some moisture is trapped, it can' mold.


== Measurements ==
== Measurements ==
Ground 13' x 22'
Ground 13' x 22'


Dry wall: (13+22)*7*2 = 490 sqft
Dry wall: (13*2+22)*7 = 336 sqft
* (2x) 13x7 → 2x2 sheets
* (1x) 22x7 → 3x2 sheets
* 2*4+6 = 14 sheets


Floor: 13*22 = 286
Floor: 13*22 = 286
Line 43: Line 89:


Chute is about 15" wide
Chute is about 15" wide
Along wall
* 32" wall
* 39" door
* 32" wall
* 64" x 24" fireplace
* 102" wall


== Buy ==
== Buy ==
https://docs.google.com/spreadsheets/d/1ZqGCZwrHoOPK3T4fSJMv9sb0Ld_IenyOJS0GakDXFJM/edit#gid=0
https://docs.google.com/spreadsheets/d/1ZqGCZwrHoOPK3T4fSJMv9sb0Ld_IenyOJS0GakDXFJM/edit#gid=0
[[Category:Projects]]

Latest revision as of 19:29, 27 September 2021

Project plan for the basement

  1. Glue up insulation
  2. Install furring
  3. Rewire lighting
  4. Install floors
  5. install gantry base
  6. install ceiling
  7. Install hardboard
  8. Install MDF battens
  9. Install bead work
  10. Caulk / fill
  11. Prime
  12. Paint

I also think I want to put in the floor before the drywall so it can go under it a little. But I should put in and seal the bottom piece first.

Build

Can Do

  • Finish horizontal furrings
  • Vertical furrings
  • Wire lights
  • Ceiling

Subfloor prep

  • Clear garage
  • Clear basement
  • Test finish

4/4/20 Subfloor

  • Buy materials
  • return truck
  • Cut support strips to width
  • Cut strips to length
  • Install

4/4/20 Shopping

  • brad nailer
  • brads
  • 10 sheets 1" insulation
  • 10 sheets 1/2" OSB
  • 10 sheets 1/8" plywood veneer
  • 2 sheets 3/4" plywood
  • moisture barrier & tape (322 sqft)

Reference

Lights

I want to move the lights from the ceiling to wall sconces. To run this behind the furring requires that I use mc cabling.

Bar/Cabinets

The entire space will be storage. One tall cabinet, a wine cabinet, fold down bar and a tall cabinet.

The cabinets should be fairly straight forward, though I'm a bit nervous about the hinges.

The wine cabinet will have glass and lighting, possibly temperature control.

The bar will be the complicated part. The bottom will just be a cabinet with a fridge. The top will be a fold down bar. I'd really like a parallel mechanism for the legs, but I'm not sure that's possible.

I also need a lock for the wine cabinet and the bar. I think I could do this with servos.

TV

Not much, but I'd like to repaint the chimney, put up shelves for the speakers and put up something to hold the cabling.

It may be worth putting up a facade of brick or stone.

Floor

First, put down a moisture barrier. Leave a bit around the edges.

The subfloor will contain the insulation. I think this will be easiest to build in the garage then assemble in the basement. Each section is the size of a sheet of OSB, except for the area around the edges. Each section has a frame running around the edges and two down the center for support. Alex is coming up on 4/4/20 to help with this.

The surface will be thin plywood cut in 6" strips. After cutting, I'll go back over the board and cut a slight chamfer to create a small gap between the boards. The strips can be sanded in the garage. I'll stain and seal them in the basement. I'll need to do a few tests. My plan is a darker stain and oil base poly seal. My plan is to just glue the floor down.

Measurements

Ground 13' x 22'

Dry wall: (13*2+22)*7 = 336 sqft

  • (2x) 13x7 → 2x2 sheets
  • (1x) 22x7 → 3x2 sheets
  • 2*4+6 = 14 sheets

Floor: 13*22 = 286

Bar area: 8'6"W x 7'T x 2'D

Pipe is about 20" wide, 55" high.

Chute is about 15" wide

Along wall

  • 32" wall
  • 39" door
  • 32" wall
  • 64" x 24" fireplace
  • 102" wall

Buy

https://docs.google.com/spreadsheets/d/1ZqGCZwrHoOPK3T4fSJMv9sb0Ld_IenyOJS0GakDXFJM/edit#gid=0