=Interior= | =Interior= | ||
#Cover tires in concrete and fill gaps with bottles | #Cover tires in concrete and fill gaps with bottles | ||
#Cover floor in moisture barrier before pouring concrete | #Cover floor in moisture barrier before pouring concrete | ||
#Concrete floor | #Concrete floor | ||
##Frame sections (note that areas under the doors and any thing outside need to be separate pieces for insulation purposes) | ##Frame sections (note that areas under the doors and any thing outside need to be separate pieces for insulation purposes) | ||
##Concrete is not poured over planters | ##Concrete is not poured over planters | ||
#Dig | #Planters | ||
#Can/bottle planter walls | ##Dig down planters | ||
##Line with plastic | |||
##Install well pump | |||
##Fill with gravel upto 4" from plumbing trench | |||
##Run plumbing into planters so water falls 4" onto gravel, place bucket guard around plumbing | |||
##Aluminum mesh | |||
##Can/bottle planter walls | |||
##Fill with dirt and plants | |||
#Walls (drywall) | #Walls (drywall) | ||
#Electrical | #Electrical | ||
| Line 133: | Line 139: | ||
###Run water | ###Run water | ||
###Connect drain | ###Connect drain | ||
##Oven/stove | ##Oven/stove | ||
#Install fireplace - The chimney and outside air pipe are already in place, potbelly stove just needs to be hooked up | #Install fireplace - The chimney and outside air pipe are already in place, potbelly stove just needs to be hooked up | ||
# | #Bottle wall on main room | ||
=Post-Move In= | =Post-Move In= | ||
Revision as of 18:45, 25 June 2012
This is intended to be a detailed guide to how we will build our Earthship.
Timing
Best to buy land late in the year. This gives us winter to get building permits in place, spring to get the lay of the land and find the water table, then we can dig out the footprint as soon as the ground thaws and start pounding tires before it gets too hot.
Prototyping
- Water systems (this can be done before land)
- Water tank
- Build or order WOM
- Water pressure
- Send it out to a garden hose
- Build a root cellar with tire walls (make it north facing to keep it really cool)
- Lay tires
- Dig it out
- Cement the inside
- Put on roofing
Pre-Tires
- Do this (http://www.instructables.com/id/low-tech-3d-scanner-for-your-building-site/) to get a site survey
- Build work shed (2x4 frame with plywood walls. Simple) if there isn't one already
- Start collecting used water bottles (do we need this?)
- Run Electrical to the shed (if we're hooking up to mains, if not, jump to electrical)
- Stake out footprint
- Dig down to below frost line
- Get a backhoe
- Dig down below frost line
- Pile dirt around footprint (for later use pounding tires)
- Dig stem wall trench and plumbing trench.
- Tamp and level ground
- Bury fireplace inlet and drain pipe for showers/tubs
Tires
- Get tires and organize by size (or get all the same size tires)
- Layout and fill first row of tires. For each tire (here's a great video http://www.youtube.com/watch?v=cer3WKTOcy8):
- Position tire offset from previous row and 1" back
- Place cardboard in the bottom of the tire
- Screw the cardboard and tire in place (screw into previous row)
- Fill with dirt
- Pound dirt with sledge hammer
- Check level
- Add more dirt and repeat
- Its very important that each tire is level.
- Place drainage pipes - (I had it wrong, these are cooling pipes, which may not be necessary)
- Second row
- Third row
- Place thermal wrap
- Remaining tires and thermal wrap
- 3-4 weeks before tires, buttresses and stem wall are done, order the trusses
- Concrete buttresses
- Set the anchor bolts in the top tires and fill them with concrete
- After the concrete has dried, cover the tires in 2mil plastic, staple in place
- Place top plate of wood on tires (Vol.1 p102)
Framing
- Stem wall
- Dig stem wall trench
- line with plastic
- Build rebar cage
- Place rebar and Pour concrete
- Place support beams (in line with front of tires)
- Place roof supports
- Frame windows
- Beams should be in place above and below windows
- Place and square wood between each window (make sure it's square, can't check this enough times)
- Put in wood for windows with operable opening
- Put notching planks in place to hold window
- Deck roof (use screws not nails)
- Place skylights
Roof
- --Chimney--?
- Roof Layers (as I understand it):
- Metal roof
- OSB filler, pine perlins and heating tubes
- Hard insulation (poly-iso)
- Waterproof asphalt felt or tar paper
- Roof decking
- Trusses
- X bracing between trusses
- Insulation
- Vapor barrier
- Ceiling
- Decorative tin ceiling
- Skylights
- Frame skylight
- Build glass top
- Weight skylight
- Rope
- Gutters (leading in to pools)
Windows
- Place windows
- Seal windows
- Place outside wood (to hold windows in place)
- Aluminum flashing
Interior
- Cover tires in concrete and fill gaps with bottles
- Cover floor in moisture barrier before pouring concrete
- Concrete floor
- Frame sections (note that areas under the doors and any thing outside need to be separate pieces for insulation purposes)
- Concrete is not poured over planters
- Planters
- Dig down planters
- Line with plastic
- Install well pump
- Fill with gravel upto 4" from plumbing trench
- Run plumbing into planters so water falls 4" onto gravel, place bucket guard around plumbing
- Aluminum mesh
- Can/bottle planter walls
- Fill with dirt and plants
- Walls (drywall)
- Electrical
- Purchase PV panels, batteries and inverter
- Install PV panels
- Setup batteries in a utility room
- Setup inverter
- Run wiring to the house as needed
- Plumbing
- Install pumps to get water out of cisterns
- Install WOM
- Water pressurizer
- Run the whole thing out to a garden hose, use that for watering plants
- Bathrooms
- Run water to bathroom and put water heater in
- Bathtub
- Install bathtub
- Run water to shower nozzle
- Run drain outside
- Sink
- Install sink unit
- Run water
- Run drains
- Bathtub
- Kitchen
- Hot water at source
- Kitchen Sink
- Install sink
- Install disposal
- Run water
- Connect drain
- Oven/stove
- Install fireplace - The chimney and outside air pipe are already in place, potbelly stove just needs to be hooked up
- Bottle wall on main room
Post-Move In
- Water trench (so that water will flow around the house and not soak up and through)
- Wind Power
- Solar water pre-heater