Shelves and surface are complete. Currently in progress are the tool stands and covers.
Shelves and surface are complete. Currently in progress are the tool stands and covers.
*Miter saw stand and leaf
*Miter saw stand and leaf - Stand is nearly complete. Need to build the leaf
*Scroll saw stand and leaf
*Scroll saw stand and leaf
*Plunge router leaf
*Plunge router leaf

Revision as of 19:01, 2 April 2012

Shelves and surface are complete. Currently in progress are the tool stands and covers.

  • Miter saw stand and leaf - Stand is nearly complete. Need to build the leaf
  • Scroll saw stand and leaf
  • Plunge router leaf
    • Need to buy a router and some bits